防閉塞裝置 倉(cāng)壁振動(dòng)器振動(dòng)電機(jī)安裝、調(diào)節(jié)、保養(yǎng)及注意事項(xiàng)
防閉塞裝置 倉(cāng)壁振動(dòng)器振動(dòng)電機(jī)安裝、調(diào)節(jié)、保養(yǎng)及注意事項(xiàng):
the warehouse wall vibrators installation and maintenance instructions
he warehouse wall vibrators installation and maintenance instructions
Warehouse wall vibrator, also known as discharge blocking device, is a vibration motor as vibration source of energy-saving products, it uses high-frequency vibration and wallop force, effectively eliminate bridging material since the inner friction, deliquescence, charged, segregation and other reasons caused by doming, clogging, so that the material discharged from the hopper mouth smoothly, ensure the equipment necessary for a stable supply.
First, the warehouse wall vibrators installation, adjustment, maintenance and precautions:
1.倉(cāng)壁振動(dòng)器焊接在全鋼板料倉(cāng)的倉(cāng)壁上 1.Wall vibrator should welded on steel plate silo wall warehouse
2.一臺(tái)倉(cāng)壁振動(dòng)器的振動(dòng)力傳遞范圍為(4~5)m,用戶(hù)可根據(jù)料倉(cāng)的大小確定每個(gè)料倉(cāng)應(yīng)安裝的臺(tái)數(shù)。安裝部位周長(zhǎng)小于4米的安裝1臺(tái)裝置即可,大于4米的每隔4~6米安裝1臺(tái)。
2.Vibration force transmission range of a warehouse wall vibrator is (4-5) meters, users can determine the number of units should be installed in each silo according to the size of the silo. One unit need to be installed for places with perimeter less than 4 meters;for greater than 4 meters, one unit should be installed every 4 to 6 meters.
3.如果兩臺(tái)倉(cāng)壁振動(dòng)器對(duì)稱(chēng)安裝在倉(cāng)壁的兩側(cè)面上時(shí),安裝位置應(yīng)上下錯(cuò)開(kāi)50~100mm,以避免互相干擾。3.If two warehouse wall vibrators are installed symmetrically on both sides of the silo wall, installation location should be staggered up and down 50 ~ 100mm, in order to avoid mutual interference.
4.倉(cāng)壁振動(dòng)器應(yīng)牢固焊接在料倉(cāng)的側(cè)壁板上,焊縫的焊肉厚度等于料倉(cāng)厚度為佳。
4. The warehouse wall vibrators should be firmly welded silo sidewall. The plate welds thickness is better equal to the thickness of the silo
5.焊接前應(yīng)檢查裝置的底板與料倉(cāng)側(cè)壁是否貼合緊密。貼縫間隙應(yīng)小于1mm,否則應(yīng)對(duì)底板進(jìn)行校正。
5.Before welding it should be checked if the backplane and silo sidewall fit tightly. Stickers seam gap should be less than 1mm, otherwise the backplane should be corrected.
6.焊接后應(yīng)有消除焊接應(yīng)力的措施,如對(duì)焊接部分局部加溫,逐漸冷卻或連續(xù)重復(fù)敲擊焊縫等。
6.After soldering it should eliminate welding stress, for example, local heating of the weld part, gradually cooling or continuously repeated welds and other percussion.
7.倉(cāng)壁振動(dòng)器中的振動(dòng)電動(dòng)機(jī)與臺(tái)架采用螺栓連接。安裝時(shí)應(yīng)牢固可靠,并有防松措施。
7.The vibrating motor of warehouse wall vibrators and carriage are connected with bolts. Installation should be solid and reliable, and have anti-loosening measures.
8.倉(cāng)壁振動(dòng)器中的振動(dòng)電動(dòng)機(jī)的引出電纜,在引出部分不允許突然彎曲,彎曲半徑應(yīng)大于電纜外徑的8-9倍。
8.The lead cables of vibrating motor of warehouse wall vibrators, do not allow a sudden bend in the lead-out portion, bend radius should be greater than 8-9 times of the cable diameter.
本表是按料倉(cāng)上端被固定,下部為游離狀態(tài)的結(jié)構(gòu)計(jì)算的,故不適用于在料倉(cāng)上下均勻被固定著的結(jié)構(gòu)。
Third, this table is based on the structure, which uppper is fixed and the lower part is in free state. It's not applicable for those structures which both sides are fixed.